Stone work and ironmongery work on the front elevations
of the building.
|
|
|
Guttering not yet replaced
|
Old guttering on left, new on the right.
|
Replaced stone showing detailed cutting required
|
 |
 |
|
 |
|
Above: All the non-original windows on this level are to be replaced
with timber sash windows.
Left: Details of the dentils between the 2nd and 3rd floors on the Hillside Crescent elevation. These are all badly
eroded and will all be replaced. |
|
|
 |
|
| Repointing on the 2nd floor |
Stone window blank removed for replacement. This is being done on each level. Note the
high quality of the original bricklaying behind! |
|
|
 |
|
|
Above: First floor. Stone sills and panels beneath are being replaced
on several of the windows on this level.
Right: New guttering and downpipes ready to be put on.
Far right: Note variation in colour of original stonework
|
|
 |
|
|
|
 |
| Above: Eroded stone marked for replacement. |
Above: Original metal girder above window on ground floor level to support the different
layout of windows on levels above.
Below: Another eroded stone requiring replacement. |
Below: Eroded stone cut out and ready to receive replacement. |
|
|
|
 |